What is "Staff Capacity"

Staff Capacity - How Many Reservations can START at the same time

What is Staff Capacity

Staff capacity is how many reservations can start at the same time. 

How to set Staff Capacity

Staff capacity is a package level setting found in the packages calendars.

Package -> Calendar -> Staff Capacity

Examples

If we have a package with Staff Capacity = 1, that means that this package can be the only package starting at this time. If there is a reservation at 5pm, the package with staff cap = 1 cannot also start at 1. 

If we have a package with Staff Capacity = 2, that means that there can be one other reservation starting at that time. If that reservation takes up 3 different resources, that is totally fine. Staff cap looks at reservations, not resources. In this example, if there was one reservation at 5pm, our package with staff cap = 2 can also be reserved at 5pm. But if there are reservations booked at 5pm, our staff cap = 2 reservation cannot start at 2.

Staff cap only looks at start times. So if we have a package with staff cap = 2, and there are 5 different reservations going on at 5 pm, as long as no other packages are starting at 5pm, we can reserve our staff cap = 2 reservation at 5 (so long as there are resources available)